Other Information
The following is historical information about NSTAR's electric system and key milestones.
- NSTAR's Highest Historical Peak Load: 4,978 MW (July 22, 2011)
- 3% Private Net Metering Cap: 149.34 MW (3% of highest historical peak load)
- 3% Public Net Metering Cap: 149.34 MW (3% of highest historical peak load)
Net Metering Totals as of March 1, 2013:
3% Private Net Metering Cap (149.34 MW cap):
- Projects Online: 37.59 MW
- Projects with Applications Submitted: 117.75 MW
- Total (both above): 155.34 MW
3% "Public" Net Metering Cap (149.34 MW cap):
- Projects Online: 33.13 MW
- Projects with Applications Submitted: 131.29 MW
- Total (both above): 164.42 MW